Lawsuit: Pending Fletchingrs v. UrbanDesign [2026] DCR 27

Brzzzes

Citizen
Aventura Resident
Grave Digger
Brzzzes
Brzzzes
Barrister
Joined
Nov 28, 2022
Messages
6

Case Filing


IN THE FEDERAL COURT OF THE COMMONWEALTH OF REDMONT
CIVIL ACTION

Fletchingrs
Plaintiff

v.

UrbanDesign (Represented by Kiwi_Boi_Gamer)
Defendant

COMPLAINT
The Plaintiff complains against the Defendant as follows:

WRITTEN STATEMENT FROM THE PLAINTIFF

"On or about February 26, 2026, I entered into a professional agreement with UrbanDesign to renovate my property at S079. Despite inspecting the site days prior and knowing exactly what the job required, the Defendant sat on the project for three days, performed zero structural work, and then quit using dishonest excuses about 'permissions' and 'complexity.' This wasn't just a change of heart; it was a bad-faith abandonment that cost me time and money. While they returned my deposit, that doesn't fix the days of lost progress or the fact that I now have to pay more for a new builder to fix their mess. I am seeking full compensation for the time wasted and the legal fees I've been forced to incur to hold them accountable."

I. PARTIES

Fletchingrs (Plaintiff) - Legal leaseholder of Plot S079.

UrbanDesign / Kiwi_Boi_Gamer (Defendant) - Contractor hired for renovation services.

II. FACTS

On or about February 23, 2026, the Defendant conducted an on-site inspection of Plot S079, explicitly noting the floor height requirements and plot dimensions.

On or about February 25, 2026, the Parties executed a binding Renovation Contract for a total sum of D$21,000.

Between on or about February 25, 2026, and on or about February 28, 2026, the Defendant held active "Member" permissions on the plot but failed to perform any material structural work.

On or about February 28, 2026, the Defendant unilaterally terminated the agreement, claiming the project was "too big"—an excuse directly contradicted by their own prior inspection.

On or about March 1, 2026, the Plaintiff was forced to mitigate damages by securing a new builder (Wayne Kerr) for the same scope of work at a higher cost of D$22,500.

III. CLAIMS FOR RELIEF

Material Breach of Contract: The Defendant failed to perform the core structural obligations of the agreement (Section 5.9), resulting in a total failure of consideration.

Breach of the Covenant of Good Faith and Fair Dealing: The Defendant utilized dishonest pretexts regarding building permissions to escape a vetted professional obligation.

Estoppel: The Defendant is legally barred from claiming "unforeseen complexity" after having performed a site survey on or about Feb 23.

Liability for Cost of Cover: Under Redmont law, a breaching party is liable for the price difference between the original contract and the replacement contract required to finish the work.

IV. PRAYER FOR RELIEF
The Plaintiff seeks the following from the Defendant:

Lost Opportunity Costs: D$6,000.00 (For 3 days of total plot inactivity at D$2,000/day).

Cost of Cover: D$1,500.00 (Price difference between original and replacement contract).

Punitive Damages: D$3,550.00 (For bad-faith conduct and deceptive trade practices).

Legal Fees: D$4,050.00 (Broken down as: D$300 Contract Review, D$750 Discovery, D$1,000 Filing, D$2,000 Trial Representation.

Total Sum Requested: D$15,100.00

Evidence:

Exhibit A: Renovation Contract signed on or about Feb 25, 2026. (Contract added as an attachment.)

Exhibit B: New Master Construction Indenture with Wayne Kerr dated on or about Mar 1, 2026. (Contract added as an attachment.)

Exhibit C: Discord logs confirming inspection on or about Feb 23, 2026, and termination on or about Feb 28, 2026.
image2.png
image3.png
image4.png
image5.png
image7.png
image6.png
image9.png
image8.png
Screenshot 2026-02-28 at 10.26.37 AM.png

Exhibit D: Incomplete building sections

Witnesses: N/A

Fletchingrs (Plaintiff)

Wayne Kerr (Secondary Contractor - to testify on project feasibility)

By making this submission, I agree that I understand the penalties of lying in court and the fact that I am subject to perjury should I knowingly make a false statement in court.

DATED: This 2nd day of March 2026

 

Attachments

Last edited:
@Brzzzes please provide proof of representation within 72 hours.
 

Writ of Summons

@Kiwi_Boi_Gamer, is required to appear before the District Court in the case of Fletchingrs v. UrbanDesign [2026] DCR 27

Failure to appear within 72 hours of this summons will result in a default judgement based on the known facts of the case.

Both parties should make themselves aware of the Court Rules and Procedures, including the option of an in-game trial should both parties request one.

 
Present your Honour,
I've been authorised by Urban Design's Director (DaanBanaan5673) to represent them.
 

Attachments

  • Urban Design Company Docket.PNG
    Urban Design Company Docket.PNG
    21.2 KB · Views: 4
  • UrbanDesign Consent.JPG
    UrbanDesign Consent.JPG
    10.5 KB · Views: 4

Answer to Complaint


IN THE DISTRICT COURT OF THE COMMONWEALTH OF REDMONT
ANSWER TO COMPLAINT

Fletchingrs (represented by Brzzzes)
Plaintiff

v.

UrbanDesign (Represented by Kiwi_Boi_Gamer)
Defendant


I. FACTS

All dates are formatted dd/mm/yyyy. Times are formatted 12:00 in Central European Time (GMT+1)

1. Affirms
that before signing the contract the Defendant did inspect the property then explicitly mentioned the plot’s “max height limit” (A-009) and suggested increasing floor heights (A-012); Noting the increased floor height was included in the contract (clause 5.9) and the contract is the complete agreement between the parties which supersedes all prior “written or oral” agreements (clause 13).

2. Affirms that on 26/2/2026 at 2:52AM (A-003) the parties signed the Renovation Contract, which fulfilled all the requirements of formation (Contracts Act), Noting that consideration (clause 11) was established and cannot be invalidated or revoked.

3. Affirms no structural work was done Noting that the Defendant was only given permissions on 28/2/2026 (A-006) and after permissions were granted there were ongoing negotiations (A-006).

4. Affirms we gave notice to terminate the contract (clause 8) on the 28/2/2026 at 4:06PM (A-007) Noting that either party could have given notice to "unilaterally" terminate the contract at any time (clause 8) and the Defendant returned the $9k non-refundable deposit (clause 8) as a show of “goodwill” (A-007 & A-022).

5. Except as hereinbefore expressly affirmed or expressly neither affirmed nor denied, each and every other factual allegation and claim for relief is Denied as if set out herein.


II. DEFENCES
Defendant asserts these defences in the alternative and reserves the right to amend/add defences as facts and discovery develops.

1. Unavailable Cause of Action: The Plaintiff claims there was a “material” breach of contract, but the Defendant never failed to perform their obligations. The Defendant validly terminated the contract (clause 8) before the “5-day deadline” (A-003 & A-007). All obligations ended after termination; it is impossible to breach obligations you don't have.

2. Failure to State a Claim: The Plaintiff has failed to provide any evidence of dishonesty, lack of integrity, or unfairness that has breached the implied covenant of Good Faith and Fair Dealing (Contracts Act). The Defendant acted in good faith and honestly throughout their business transaction.

3. Unavailable Cause of Action: Estoppel has not been recognised as a legitimate cause of action within DemocracyCraft and has been expressly rejected by the Supreme Court [1950minecrafter v. Commonwealth of Redmont [2021] SCR 18]. Although Collateral Estoppel (rule 5.9) does exist, it is not a cause of action but rather a procedural rule.

4. Unavailable Cause of Action: The Plaintiff claims "Cost of Cover" is both a legitimate cause of action and remedy under "Redmont Law" without providing any Acts or cases to support their claim. The burden of proof is on the Plaintiff to establish proper authority and as none has been provided the "Cost of Cover" cause of action is unjustified and must fail.

6. Lack of Damages: The Plaintiff lost no money from the termination; they were made whole after the 9k non-refundable deposit was returned. The Plaintiff only started losing money after they decided to take legal action. Both parties lost an equal amount of time in this transaction.

7. Speculative Damages: The Plaintiff claims to have suffered "lost opportunity costs” but has failed to explain what "opportunity" exactly was lost. The Plaintiff has failed to provide any evidence justifying the "$2,000 per day" figure for "plot inactivity"; the figure has no logical basis.

8. Punitive Damages not Warranted: Defendant did not act with the requisite malice/outrageousness to justify punitive damages, and any punitive damages request is excessive, unsupported, and contrary to governing damages principles.


III. Evidence

A-003.png
A-006.png
A-007.png
A-009.png
A-012.png
A-022.png


IV. Witness List
1. Fletchingrs
2. sarf123


V. Attestation
By making this submission, I agree and understand the penalties of lying in court and the fact that I am subject to perjury should I knowingly make a false statement in court.

DATED: 18th March 2026 (UTC+12:00)

 

Attachments

Back
Top