IN THE COURT OF THE COMMONWEALTH OF REDMONT
CIVIL ACTION
cjcroft
(pugbandit Representing)
Plaintiff
v.
YoungBuck2k
Defendant
COMPLAINT
The Plaintiff complains against the Defendant as follows:
The Plaintiff complains against the Defendant as follows: The Defendant had agreed to a payment for a service to the Plaintiff which has not been received and this has halted business and multiple attempts to reach out to Defendant were also made before taking this to the court.
I. PARTIES
1. Cjcroft
2. YoungBuck2k
II. FACTS
1. YoungBuck2k placed an order at Design Studio.
2. The price that was agreed to pay was 5000$
3. YoungBuck2k went inactive and did not pay.
4. Materials were already bought for the project YoungBuck2k wanted.
5. Multiple attempts were made to contact YoungBuck2k for payment.
6. After failure to respond the Plaintiff had no chance but to take this to court.
III. CLAIMS FOR RELIEF
1. The defendant gave his signature and acknowledged the contract’s existence
2. The defendant has not fulfilled their part of the contract and has breached the contract and agreement that was done with the Plaintiff.
IV. PRAYER FOR RELIEF
The Plaintiff seeks the following from the Defendant:
1. $5000 for payment for resources and the agreed work which was done
2. $2000 for damage caused to the business in the time and legal fees.
	
	
		
			
		
		
	
	
		
	
		
	
	
	
		
			
		
	
		
	
	
	
		
			
		
	
		
	
	
	
		
			
		
	
		
	
		
	
				
			CIVIL ACTION
cjcroft
(pugbandit Representing)
Plaintiff
v.
YoungBuck2k
Defendant
COMPLAINT
The Plaintiff complains against the Defendant as follows:
The Plaintiff complains against the Defendant as follows: The Defendant had agreed to a payment for a service to the Plaintiff which has not been received and this has halted business and multiple attempts to reach out to Defendant were also made before taking this to the court.
I. PARTIES
1. Cjcroft
2. YoungBuck2k
II. FACTS
1. YoungBuck2k placed an order at Design Studio.
2. The price that was agreed to pay was 5000$
3. YoungBuck2k went inactive and did not pay.
4. Materials were already bought for the project YoungBuck2k wanted.
5. Multiple attempts were made to contact YoungBuck2k for payment.
6. After failure to respond the Plaintiff had no chance but to take this to court.
III. CLAIMS FOR RELIEF
1. The defendant gave his signature and acknowledged the contract’s existence
2. The defendant has not fulfilled their part of the contract and has breached the contract and agreement that was done with the Plaintiff.
IV. PRAYER FOR RELIEF
The Plaintiff seeks the following from the Defendant:
1. $5000 for payment for resources and the agreed work which was done
2. $2000 for damage caused to the business in the time and legal fees.