IN THE FEDERAL COURT OF THE COMMONWEALTH OF REDMONT
CIVIL ACTION
Mestiere (Bombaz2005 and jediflashfire representing)
Plaintiff
v.
zeos_exe
Defendant
COMPLAINT
The Plaintiff complains against the Defendant as follows:
zeos_exe signed a contract for a build for $19,900 which I have completed, and he has not payed me in the due date for the money (2 weeks), therefore he owes me an additional $10,000.
I. PARTIES
1. Mestiere (Bombaz2005 and jediflashfire representing)
2. zeos_exe
II. FACTS
1. The plaintiff had built something for the defendant, with a contract stipulating that the defendant would pay the plaintiff $19,900 three weeks (21 days) later.
2. On July 11th, the due date for the defendant to pay, the defendant refused to pay, saying that he had been fined and could not pay.
3. Article II of the contract stipulates that if a party breaches the contract, the nonbreaching party is entitled to $10,000 and any legal fees included.
4. The plaintiff waited a day for the defendant to pay, then brought the case to the Redmont Law Firm.
III. CLAIMS FOR RELIEF
1. The defendant has breached the contract, and has thus triggered article II of the contract.
IV. PRAYER FOR RELIEF
The Plaintiff seeks the following from the Defendant:
1. Payment of $19,900 dollars as payment for the loan
2. Payment of $10,000 dollars as stated by article II of the contract
3. Payment of $1,250 in legal fees
Exhibit A-E: Contract
Exhibit F-J: Messages
By making this submission, I agree I understand the penalties of lying in court and the fact that I am subject to perjury should I knowingly make a false statement in court.
DATED: This 4th day of August, 2022
CIVIL ACTION
Mestiere (Bombaz2005 and jediflashfire representing)
Plaintiff
v.
zeos_exe
Defendant
COMPLAINT
The Plaintiff complains against the Defendant as follows:
zeos_exe signed a contract for a build for $19,900 which I have completed, and he has not payed me in the due date for the money (2 weeks), therefore he owes me an additional $10,000.
I. PARTIES
1. Mestiere (Bombaz2005 and jediflashfire representing)
2. zeos_exe
II. FACTS
1. The plaintiff had built something for the defendant, with a contract stipulating that the defendant would pay the plaintiff $19,900 three weeks (21 days) later.
2. On July 11th, the due date for the defendant to pay, the defendant refused to pay, saying that he had been fined and could not pay.
3. Article II of the contract stipulates that if a party breaches the contract, the nonbreaching party is entitled to $10,000 and any legal fees included.
4. The plaintiff waited a day for the defendant to pay, then brought the case to the Redmont Law Firm.
III. CLAIMS FOR RELIEF
1. The defendant has breached the contract, and has thus triggered article II of the contract.
IV. PRAYER FOR RELIEF
The Plaintiff seeks the following from the Defendant:
1. Payment of $19,900 dollars as payment for the loan
2. Payment of $10,000 dollars as stated by article II of the contract
3. Payment of $1,250 in legal fees
Exhibit A-E: Contract
Exhibit F-J: Messages
By making this submission, I agree I understand the penalties of lying in court and the fact that I am subject to perjury should I knowingly make a false statement in court.
DATED: This 4th day of August, 2022